Progress

Construction tracker

A verified view of where the island actually is — using the developer's own published percentages alongside the regulator's independent inspection figures.

Overall progress

26.75%

Superstructure works are advancing across all fronds, with villas becoming increasingly defined along the waterfront. Internal and external finishing works have commenced on selected units.

By frond · developer inspection 10 March 2026

Frond K

27.71%

RERA 25.11% · 27 January 2026

Frond L

24.71%

RERA 24.71% · 27 January 2026

Frond M

22.10%

RERA 19.73% · 27 January 2026

Frond N

29.20%

RERA 24.20% · 27 January 2026

Frond O

37.44%

RERA 31.45% · 27 January 2026

Frond P

20.50%

RERA 15.60% · 27 January 2026

By work package

Substructure

93.27%

Superstructure

68.40%

Building work

21.64%

MEP work

18.76%

Infrastructure

65.05%

Phases

Where each workstream stands

  1. Land reclamation & frond formation

    Substantially advanced

  2. Marine works & shoreline protection

    In progress

  3. Primary roads & spine infrastructure

    In progress

  4. Villa construction

    Phased — verification pending

  5. Apartments, retail & hospitality

    Announced

Connectivity

Drive times from the island

Published journey times from the developer. Real-world times vary with the access road build-out.

Ibn Battuta Mall

19 min

Al Maktoum International Airport (DWC)

24 min

Expo City

24 min

Dubai Marina

25 min

Palm Jumeirah

27 min

Nearest metro station

16 min