Progress
Construction tracker
A verified view of where the island actually is — using the developer's own published percentages alongside the regulator's independent inspection figures.
Overall progress
26.75%
Superstructure works are advancing across all fronds, with villas becoming increasingly defined along the waterfront. Internal and external finishing works have commenced on selected units.
By frond · developer inspection 10 March 2026
Frond K
27.71%
RERA 25.11% · 27 January 2026
Frond L
24.71%
RERA 24.71% · 27 January 2026
Frond M
22.10%
RERA 19.73% · 27 January 2026
Frond N
29.20%
RERA 24.20% · 27 January 2026
Frond O
37.44%
RERA 31.45% · 27 January 2026
Frond P
20.50%
RERA 15.60% · 27 January 2026
By work package
Substructure
93.27%
Superstructure
68.40%
Building work
21.64%
MEP work
18.76%
Infrastructure
65.05%
Phases
Where each workstream stands
Land reclamation & frond formation
Substantially advanced
Marine works & shoreline protection
In progress
Primary roads & spine infrastructure
In progress
Villa construction
Phased — verification pending
Apartments, retail & hospitality
Announced
Connectivity
Drive times from the island
Published journey times from the developer. Real-world times vary with the access road build-out.